Skip to content
Sachi Academy
Module 2 · Chapter 2.4

Building plan approval in Bangalore: who sanctions it and what to check

By Sachi Academy team · 7 min read · Last checked

Sachi's short answer

Building plan approval is the sanction that lets a builder construct a building as drawn. Inside the Greater Bengaluru Area, the City Corporation Commissioner grants it under the Greater Bengaluru Governance Act, 2024. The sanction is valid for five years. Check the sanctioned plan on the K-RERA page against the brochure before you book.

In this lesson 5 sections
  1. 2.4.1 Who approves a building plan in Bangalore?
  2. 2.4.2 How long is a building plan sanction valid, and how fast is it issued?
  3. 2.4.3 What happens between the sanction and the occupancy certificate?
  4. 2.4.4 How do you match the sanctioned plan with the K-RERA page?
  5. 2.4.5 What if the brochure differs from the sanctioned plan?

2.4.1 Who approves a building plan in Bangalore?

Inside the Greater Bengaluru Area, the Commissioner of the City Corporation approves a building plan. The Greater Bengaluru Governance Act, 2024 sets this rule. Section 228 says no person can construct a building in a City Corporation area except under the Act and the building bye-laws. Under Section 229, the builder applies to the Commissioner with the site plan, floor plans, elevations, sections and specifications. Section 230(2) says the Commissioner decides on the advice of the Additional Chief Town Planner. The plan must conform to the Act, the master plan and the building bye-laws. The Commissioner can refer an application to the Chief Commissioner of the Greater Bengaluru Authority (GBA). Section 14(2) makes the GBA the Planning Authority for the Greater Bengaluru Area. The GBA can approve layouts, and the City Corporation sanctions the buildings. Outside the Greater Bengaluru Area, a different planning authority and local body apply. Sachi did not check those authorities for this chapter.

StepWho actsSection of the Greater Bengaluru Governance Act, 2024
Layout approvalGreater Bengaluru Authority, as Planning Authority14(2)(b)
Building plan applicationBuilder, to the City Corporation Commissioner229, 230(1)
Scrutiny of the planAdditional Chief Town Planner advises the Commissioner230(2)
Sanction or rejectionCity Corporation Commissioner230(2), 231
Plinth certificateCommissioner, after a site inspection at plinth level239
Occupancy certificateCommissioner, after an inspection of the finished building241

2.4.2 How long is a building plan sanction valid, and how fast is it issued?

A building plan sanction inside the Greater Bengaluru Area is valid for five years. Section 230(6) of the Greater Bengaluru Governance Act, 2024 says that after five years, the builder must apply for permission again. This matters for a new flat. If the sanction is old and the building is far from complete, ask the builder for the fresh permission. Section 231 sets the time for a decision. The Commissioner must grant or refuse the permission by written order within 30 days of the application. If no order comes, the applicant can write to the Commissioner, who then has 15 more days. If there is still no decision, the applicant can ask the Chief Commissioner, who must decide within one month. If the Chief Commissioner also does not decide, the Act treats the permission as given. Even then, the building must still follow the Act and the bye-laws. Section 230(11) says a sanctioned plan is a public document, published on the City Corporation website.

RuleWhat the Act saysSection
Validity of the sanctionFive years, then a fresh permission230(6)
Time for a decision30 days, then 15 more days after a letter231(1), 231(2)
No decision at allChief Commissioner decides within one month, or the permission is deemed given231(3)
Public recordSanctioned plan published on the City Corporation website230(11)
Licence fee cap, residentialUp to 0.20 percent of the guidance value of the vacant site232(2)(a)

2.4.3 What happens between the sanction and the occupancy certificate?

After the sanction, the building passes two more checks: the plinth certificate and the occupancy certificate (OC). Section 239 of the Greater Bengaluru Governance Act, 2024 says construction cannot go above plinth level without a plinth certificate. The builder must get it within the validity of the sanction. The Commissioner inspects the site, and issues the certificate within 15 days if the work follows the sanctioned plan. If the Commissioner does not issue it in 15 days, work can go on according to the sanctioned plans. If the work differs from the plan but stays within the bye-law limits, a modified plan can be approved under Section 245. At the end, Section 241 says the builder must apply for the OC within 30 days of completion. An empanelled architect or engineer certifies the application, with as-built floor plans. The Act lets the Commissioner condone deviations of up to ten percent of the permissible limits, with a compounding fee. No one can occupy the building before the OC, unless the Commissioner does not refuse within 30 days.

  1. Ask the builder for the plinth certificate of your tower, with its date.
  2. If the plan was modified, ask for the modified plan and its approval.
  3. Before possession, ask for the OC of your tower.
  4. Compare the as-built plan in the OC file with your unit.

2.4.4 How do you match the sanctioned plan with the K-RERA page?

The K-RERA page is where a buyer can see the plan that the builder filed. Section 4(2) of the RERA Act, 2016 says the registration application must include an authenticated copy of the approvals and the commencement certificate. That is clause (c). It must also include the sanctioned plan, the layout plan and the specifications, under clause (d). For a project in phases, each phase needs its own approvals. Section 2(m) defines a commencement certificate as the permit that lets the builder begin work as per the sanctioned plan. Section 11(3)(a) says that at booking, the builder must make the sanctioned plans, layout plans and specifications available to you. On the K-RERA page, open the Uploaded Documents tab. Check that the approved plan and the commencement certificate are real files, not placeholders. Then compare them with the brochure. The K-RERA registration does not issue the sanction, so check the sanction date and authority on the document itself.

CheckWhere to lookWhat to compare
Who sanctioned the plan, and whenThe sanction order or licenceThe authority name, the date and the five-year validity
Approved planK-RERA Uploaded Documents tabTower count, floors, unit types and your unit’s position
Commencement certificateK-RERA Uploaded Documents tabThe date and the phase that it covers
Plan changesK-RERA Modification of Plan Details, on some pagesWhat changed, and whether buyers consented
PhaseK-RERA registration numberThat your tower is in the registered phase

2.4.5 What if the brochure differs from the sanctioned plan?

If the brochure differs from the sanctioned plan, treat the sanctioned plan as the record and ask the builder to explain each difference in writing. Section 14(2) of the RERA Act, 2016 protects you after the builder discloses the plans. Clause (i) says the builder cannot change the sanctioned plans, layout plans or specifications of your unit without your previous consent. Minor changes are allowed only if you ask for them, or if an authorised architect or engineer recommends them for architectural or structural reasons. The builder must then tell you. The Act says a structural change, more area or a change in height is never a minor change. Clause (ii) covers other changes to the building and its common areas. These need the previous written consent of at least two-thirds of the allottees, other than the builder. Each allottee counts once, whatever the number of flats they booked. Keep dated copies of the brochure, the plan and the K-RERA page for your lawyer.

Type of changeConsent the RERA Act requiresSection
Change to your own unitYour previous consent14(2)(i)
Minor change for structural or architectural reasonsRecommendation by an authorised architect or engineer, and notice to you14(2)(i), proviso
Change to the building or common areasPrevious written consent of two-thirds of the allottees14(2)(ii)
Structural change, more area or more heightNever counted as minor14(2)(i), Explanation

Sachi reads the plan documents that builders file on K-RERA for Bangalore projects. To compare your project’s filed plan with its brochure, Ask Sachi.

What this means for you

  • Ask for the sanctioned plan, the licence date and the commencement certificate. A brochure or an approval logo is not the sanctioned plan.
  • Check that the sanction date is less than five years old, or that the builder has a fresh permission. Section 230(6) sets the five-year validity.
  • Compare the tower count, floors and your unit's position with the plan on the K-RERA page. Any change to your unit needs your consent under Section 14(2).

Try Sachi with your home shortlist →

Progress is saved on this device.

Questions buyers ask

Who approves building plans in Bangalore?

Inside the Greater Bengaluru Area, the Commissioner of the City Corporation grants the sanction, on the advice of the Additional Chief Town Planner. Section 230 of the Greater Bengaluru Governance Act, 2024 sets this. Outside that area, a different authority applies.

How long is a building plan sanction valid in Bangalore?

Five years. Section 230(6) of the Greater Bengaluru Governance Act, 2024 says a sanctioned plan is valid for five years. After that, the builder must apply for permission again.

How long does the City Corporation take to approve a building plan?

Section 231 gives the Commissioner 30 days. If there is no order, the applicant can write, and the Commissioner gets 15 more days. If the Chief Commissioner also does not decide within one month, the Act treats the permission as given.

Does K-RERA registration prove that the building plan is valid?

No. K-RERA collects the approvals and the sanctioned plan with the registration application, under Section 4(2) of the RERA Act. The planning authority issues the sanction. Check the sanction itself and its date.

Can the builder change the plan after I book?

Only within limits. Section 14(2) of the RERA Act says changes to your unit need your consent. Other changes to the building need the written consent of at least two-thirds of the allottees.

Sources

  1. The Greater Bengaluru Governance Act, 2024 (Karnataka Act No. 36 of 2025), sections 2(46), 14(2), 228, 229, 230, 231, 232, 239 and 241 (PDF hosted by PRS Legislative Research) · checked
  2. The Greater Bengaluru Governance Act, 2024, official copy on India Code · checked
  3. Real Estate (Regulation and Development) Act, 2016, sections 2(m), 4(2)(c), 4(2)(d), 11(3)(a) and 14(2) (PDF hosted by K-RERA) · checked
  4. Karnataka Real Estate Regulatory Authority, project search and uploaded project documents · checked

Last checked:

All chapters in Module 2: Legal and approvals

Ask Sachi about this chapter